Click on images to see larger version.
|
The 8th grade Technology class of Mr. Bessette and student teacher
Rob Boak are constructing a scale model of the Harison-Morley Grist Mill.
They are using Systems and Subsystems in Technology (Module T-4, New York
State Standards). The three subsystems within the construction system are
designing,
managing, and building. The students are managing and building a 30x38"
scale model of the grist mill. The scale is 3/4" = 1 foot. They are using
a closed-loop system with building the grist mill as input, the process
being the resources needed such as: information, materials, tools, and
the output being the actual completed structure. Students are learning
the different stage of building; foundation, floor framing, wall framing,
and roof framing. The Harison-Morley Grist Mill was constructed of stone,
but the students are using modern construction techniques to build their
model. However, the exterior is planned to be finished so that it looks
like stone.

|
|